HAUSE SEWER NETWORKsewers@hause.ca403-679-3100
NewSewerLines.com
FAQ

Questions about new sewer service connections, answered

Answers to common questions about new sewer service connections for infill homes, suites, laneway houses and multiplexes in Canadian cities.

Conceptual illustration of connection questions above a building sewer and a separate main
Illustrated field guideConnection questions above a building sewer and a separate mainProject · existing line · authority · inspection
Short answer

These are the questions builders, owners and designers ask most about new sewer service connections for infill homes, secondary suites, laneway houses and small multiplexes in Canadian cities. Each answer is short and points to the guide or tool with the detail. City rules and fees are as published when checked in September 2026.

Key takeaways
  • The city decides who builds the public side, whether an old service can stay, and what it charges.
  • The plumbing code decides the minimum size and how load is counted.
  • Most delays come from applying late, not from digging.
The usual order of a new service connectionSeven steps in order. One: zoning approval and the development or building permit. Two: a servicing check against the city's records, capacity and the condition of any existing service. Three: the connection or service application and its fees. Four: utility locates. Five: the tap and the pipe laid, with the public side done under the city's rules and the private side under a plumbing permit. Six: inspection of the open work, tests and any required camera video. Seven: the record drawing, tie card and final sign-off. 1ZONING + PERMITdevelopment orbuilding permit2SERVICING CHECKrecords, capacity,existing service3APPLICATIONconnection or serviceapplication + fees4LOCATESone-call ticket,private locates5TAP + LAYpublic side by localrule, private by permit6INSPECTopen trench, tests,CCTV if required7RECORDas-built, tie card,final sign-off WAITS ARECITY-SET SEQUENCE · ILLUSTRATIVE · NAMES, ORDER AND WHO DOES EACH STEP DIFFER BY CITY Ask the city early: a servicing check can change the design before drawings are final.
Fig. 1The order a new service usually follows: zoning and permits, a servicing check against the city's records, the connection application, locates, the tap, inspection and the record drawing. The waits are set by each city.

01 /What does this FAQ cover?

New connections for new buildings and added units: the application, the size, the route, the cost, the inspection and the records. It does not cover replacing a failing lateral under an existing house in Calgary, which sister site NewSewerLine.ca covers, or the craft of laying pipe, which SewerInstall.com covers.

The usual order of a new service connectionSeven steps in order. One: zoning approval and the development or building permit. Two: a servicing check against the city's records, capacity and the condition of any existing service. Three: the connection or service application and its fees. Four: utility locates. Five: the tap and the pipe laid, with the public side done under the city's rules and the private side under a plumbing permit. Six: inspection of the open work, tests and any required camera video. Seven: the record drawing, tie card and final sign-off. 1ZONING + PERMITdevelopment orbuilding permit2SERVICING CHECKrecords, capacity,existing service3APPLICATIONconnection or serviceapplication + fees4LOCATESone-call ticket,private locates5TAP + LAYpublic side by localrule, private by permit6INSPECTopen trench, tests,CCTV if required7RECORDas-built, tie card,final sign-off WAITS ARECITY-SET SEQUENCE · ILLUSTRATIVE · NAMES, ORDER AND WHO DOES EACH STEP DIFFER BY CITY Ask the city early: a servicing check can change the design before drawings are final.
Fig. 2The order a new service follows. Most questions below belong to one of these seven steps.

For your own project, start with the Service Connection Planner and the fixture load estimator, or request quotes.

FAQAll questions

What is a new sewer service connection?

The pipe and the city approval that join a new or changed building to the public sewer: a tap on the main, a public segment to the property line and a private building sewer to the building. See what a sewer tie-in is.

Does a demolish-and-rebuild infill project need a new sewer connection?

Often. Calgary's guidelines call for new services on a rebuild, Halifax replaces services 30 years or older, and Toronto and Vancouver accept reuse only for PVC in good condition on video. See the reuse guide.

Who is allowed to connect a new service to the city main?

Only the party the city authorizes: city crews or contractors, or an approved, authorized or licensed contractor, depending on the city.

What permits does a new sewer service need?

Usually a connection approval, a plumbing or site servicing permit for the private side, and a right-of-way permit for street work. See the permit guide.

How early should the connection application go in?

During design, before the foundation depth is fixed. Several cities want it before or alongside the building permit.

What size sewer service does a fourplex need?

By the plumbing code table, a typical fourplex of about 68 fixture units fits a 4-inch building sewer at 1 in 100, which carries 180. City minimums can require larger. See sizing.

What is the smallest sewer allowed to connect to a public sewer?

NPS 4, downstream of the main cleanout, under National Plumbing Code Article 2.4.9.4.

Can a garden suite or laneway house use the main house sewer?

Usually, because the code lets an ancillary building on the same lot share the service. Some cities also allow a separate connection. See the laneway and garden suite guide.

When does each unit need its own sewer service?

When units are on separate lots or titles in every city checked, and for side-by-side units in Edmonton even on one title.

Does an infill multiplex need a storm sewer connection?

Often: Saskatoon requires one at three or more units, EPCOR a private storm system at three or more, and Calgary's Fast Track for R-CG requires storm service.

How much does the city charge for a new sewer connection?

It varies widely: Toronto $14,718.78 for a new residential sanitary connection in 2026, Vancouver $21,656 flat plus $2,200 for a house-scale connection, and review, inspection or tap fees where your contractor builds to the main.

What does the private side of a new service cost?

Typically $600 to $1,000 per metre shallow and $1,000 to $2,000 per metre deep or under hard surfaces, plus cleanouts, permits and restoration, as CAD 2026 planning estimates. See the cost guide.

How long does a new sewer connection take from application?

Toronto targets 12 to 14 weeks plus technical review; Vancouver schedules house-scale connections within 4 to 6 months after the sump inspection; EPCOR builds in 3 to 5 days once scheduled.

Will my city check whether the sewer has capacity for more units?

Some do: Saskatoon pre-reviews three or more units in listed neighbourhoods, Halifax Water can require a hydraulic analysis on a change of use, and Winnipeg asks detached-suite applicants to request a capacity assessment.

What happens to the old service when a new one is installed?

It is abandoned to the city's standard, often with a fee or deposit, such as Toronto's $1,816.50 sanitary disconnection or Winnipeg's $5,380 deposit per service.

Is a camera inspection needed for a new connection?

Not by the plumbing code for new pipe, but several cities require one to reuse an existing lateral, and a recorded run of the new service is the best record of how it was left.

Who inspects a new sewer service before backfill?

The city inspects the public connection; the plumbing inspector inspects the private building sewer. See the inspection guide.

What if the new basement is lower than the sewer main allows?

Fixtures that cannot drain by gravity go to a sealed, vented sump with a pump or ejector. See the pumped services guide.

Does adding a basement suite change the backwater valve?

Usually. A normally open backwater valve in a building drain may serve only one dwelling unit, so protection is arranged per unit or per branch. See secondary suite plumbing.

Are water and sewer applied for together?

In most cities, yes, and they usually share a trench, but they are sized, laid at different depths and inspected separately. See the water and sewer guide.

Can roof downspouts or foundation drains go into the new sanitary service?

Not in most cities for new buildings. See sanitary, storm and combined sewers.

Which code sets the sizing rules in Ontario?

The Ontario Building Code's plumbing part, rather than the National Plumbing Code directly. Alberta has had the NPC 2020 in force since April 1, 2023.

Is HAUSE a contractor that installs sewer connections?

No. HAUSE is an independent information and quote-request network. It explains the process and can pass your request to contractors; it does not do the work.

Request quotes

Describe the problem once. Get a straight answer.

Send the symptoms and anything you already know — age of the house, what a camera found, what you have been quoted. The HAUSE Sewer desk replies with next steps and, where available, a local contractor for the job.

Sewage backing up right now? Stop using water, keep people away from the water, and do not touch electrical equipment near it.

Tell us about the job

Free request. We read every one and reply by email or phone.

HAUSE Sewer is an independent network, not a contractor. See our privacy notice.

The HAUSE Sewer network

One sewer line, every angle.