Sewer connection permits: what you apply for, who applies, and what to submit

How a sewer connection permit works in Canadian cities: the approvals behind a new service, who files them, what to submit and when to apply.

Conceptual illustration of application package with a servicing plan and inspection hold-point record
Illustrated field guideApplication package with a servicing plan and inspection hold-point recordDrawings · city application · permission · inspection
Short answer

A new sewer service usually needs more than one approval: a city connection application or permit for the public side, a plumbing or site servicing permit for the private side, and often a right-of-way permit for work in the street. Who applies, and what must be submitted, depends on the building: a house or suite often goes through a simple residential route, while a multiplex usually needs engineered drawings.

Key takeaways
  • Think of three approvals: the connection itself, the private plumbing, and any work in the road or boulevard.
  • House-scale projects often have a combined or simplified route; multiplexes usually move to an engineered or commercial route.
  • Several cities want the connection application before or alongside the building permit, not after.
  • Most applications ask for a site or servicing plan, the existing services, and a utility locate or gas sketch.
  • Every city checked names the party allowed to work on the public side; unauthorized work in the right-of-way is not an option.
Sewer camera view of a branch pipe protruding into a larger sewer
IllustrationA poorly made connection: a branch pipe protrudes into the line and catches debris.
The usual order of a new service connectionSeven steps in order. One: zoning approval and the development or building permit. Two: a servicing check against the city's records, capacity and the condition of any existing service. Three: the connection or service application and its fees. Four: utility locates. Five: the tap and the pipe laid, with the public side done under the city's rules and the private side under a plumbing permit. Six: inspection of the open work, tests and any required camera video. Seven: the record drawing, tie card and final sign-off. 1ZONING + PERMITdevelopment orbuilding permit2SERVICING CHECKrecords, capacity,existing service3APPLICATIONconnection or serviceapplication + fees4LOCATESone-call ticket,private locates5TAP + LAYpublic side by localrule, private by permit6INSPECTopen trench, tests,CCTV if required7RECORDas-built, tie card,final sign-off WAITS ARECITY-SET SEQUENCE · ILLUSTRATIVE · NAMES, ORDER AND WHO DOES EACH STEP DIFFER BY CITY Ask the city early: a servicing check can change the design before drawings are final.
Fig. 1The order a new service usually follows: zoning and permits, a servicing check against the city's records, the connection application, locates, the tap, inspection and the record drawing. The waits are set by each city.

01 /What permits does a new sewer connection need?

Most new connections pass through three separate approvals, even where one application form covers them. The connection approval authorizes the tap and the pipe in the public right-of-way and sets its fee. The plumbing or site servicing permit covers the private building sewer and drains under the building code. A right-of-way or street-use permit covers excavation in the road, sidewalk or boulevard. The names change from city to city; the pattern does not.

The connection route by city (as checked September 2026)
CityHouse, suite or duplexMultiplex or larger
VancouverOne combined residential sewer and water permit, before the development and building permitSeparate commercial sewer and commercial water permits, applied for by a BC professional engineer
TorontoOnline request for a 19 or 25 mm water or 150 mm sewer connection, up to 5 unitsICI Municipal Services Application for larger services
CalgaryPlumbing permit; a "quick trench" photo-review option for single and semi-detached homesSeparate plumbing or site servicing permit and a Development Site Servicing Plan
EdmontonEPCOR Infill Water and Sewer Servicing, with a servicing plan and an Alberta One Call sheetEngineer-stamped site mechanical plan, lot grading plan and stormwater calculations
SaskatoonBuilding Application, Water and Sewer section, plus a Use of Right-of-Way PermitSame, plus a Saskatoon Water pre-review for 3+ units in listed neighbourhoods
HalifaxHRM building permit; existing homes upload a New Connection and Renewal ApplicationSection 8 of Halifax Water's Design Specifications
WinnipegCity authorization plus a Service Permit, pulled by a licensed contractorSame, with multi-family drainage requirements
OttawaCoach houses: a mandatory 3-1-1 service consultation before the building permitServicing study for development applications
The usual order of a new service connectionSeven steps in order. One: zoning approval and the development or building permit. Two: a servicing check against the city's records, capacity and the condition of any existing service. Three: the connection or service application and its fees. Four: utility locates. Five: the tap and the pipe laid, with the public side done under the city's rules and the private side under a plumbing permit. Six: inspection of the open work, tests and any required camera video. Seven: the record drawing, tie card and final sign-off. 1ZONING + PERMITdevelopment orbuilding permit2SERVICING CHECKrecords, capacity,existing service3APPLICATIONconnection or serviceapplication + fees4LOCATESone-call ticket,private locates5TAP + LAYpublic side by localrule, private by permit6INSPECTopen trench, tests,CCTV if required7RECORDas-built, tie card,final sign-off WAITS ARECITY-SET SEQUENCE · ILLUSTRATIVE · NAMES, ORDER AND WHO DOES EACH STEP DIFFER BY CITY Ask the city early: a servicing check can change the design before drawings are final.
Fig. 2Where the connection application sits in the sequence. In Vancouver and Toronto it starts early; in Calgary and Edmonton it rides with the servicing plan.

02 /Who applies for the connection?

It depends on the scale of the building and the city's model. For house-scale work the owner or builder usually applies, sometimes through the contractor. For multi-unit buildings the application tends to become professional work.

  • Owner or builder: Vancouver's residential permit for a house, duplex or laneway house; Toronto's online request for up to 5 units; Halifax's renewal form for existing single homes and townhouses.
  • Licensed or approved contractor: Winnipeg's Service Permit is tied to a licensed sewer or water contractor; Saskatoon's licensed contractors build under the Building Application; Calgary's public connections need a City-approved indemnified contractor.
  • Engineer: Vancouver's commercial sewer and water permits for multiplexes; Edmonton's stamped site mechanical plans for three or more units; Winnipeg's wastewater flow estimates, which its guidelines require to be stamped.

03 /What do you need to submit?

Requirements vary, but the same documents recur across the cities checked. Assemble them before you apply and the application moves faster.

  1. A legal survey or site plan

    Vancouver asks for a sealed legal survey dated within the last six months. Most cities want the building footprint, property lines and existing services shown.

  2. A servicing plan

    Proposed sanitary, storm and water services with sizes, slopes, inverts and the tie-in point. Saskatoon's garden suite permits ask for a utility plan certified by a Saskatchewan design professional, including line sizes, materials, slope and frost protection.

  3. The existing services

    EPCOR's infill checklist asks which existing services will be reused or abandoned, with an assessment of sanitary and storm services.

  4. Locates

    Edmonton asks for an Alberta One Call locate sheet; Vancouver asks for a gas sketch from BC One Call.

  5. Load and capacity information

    Fixture counts or peak demand for water, stormwater calculations where required, and for larger buildings a servicing report. Vancouver's water permit asks for peak domestic demand, with fire-flow calculations only where the site was rezoned.

  6. Grading and stormwater

    Edmonton requires an infill lot grading plan in mature neighbourhoods; Winnipeg requires a lot grading permit before a residential building permit; Calgary may require a stormwater management report first.

04 /When should you apply?

Earlier than most people expect. Vancouver asks you to apply for the residential sewer and water permit before the combined development and building permit, and says house-scale connections are then scheduled within 4 to 6 months after the sump inspection passes. Toronto targets completion within 12 to 14 weeks of application, not counting technical review, which takes 4 to 6 weeks for a first response. Ottawa requires its service consultation before the coach house building permit.

The reason is design, not only queues. The tie-in depth sets how deep the building drain can be, the city's answer on reuse decides whether you budget for a new service, and a capacity review can change the service size or add a storm connection. Asking after the drawings are finished risks redesign. The timeline guide puts the published waits in order.

Apply for the connection while the drawings can still change, not after the foundation is poured.

05 /Why do applications get sent back?

Usually for missing information rather than a design problem. The same gaps recur, and each one restarts part of a review clock; Toronto allows 10 business days per revision.

  1. No tie-in depth. A servicing plan that shows a connection but no invert at the main or property line cannot be checked for fall.
  2. Existing services ignored. EPCOR's checklist asks which services are reused or abandoned; leaving them off stalls the review.
  3. Storm not addressed. Multi-unit projects that need a storm connection or stormwater calculations and show neither.
  4. Wrong route for the building type. A multiplex filed through a house-scale route, or a duplex on separate titles shown sharing one service.
  5. Out-of-date survey. Vancouver wants a legal survey dated within six months.

06 /What does the permit cost?

Application and permit fees are usually small beside the connection itself, but they are the first money spent. As checked in September 2026: Vancouver's sewer application fee is $2,200, non-refundable; Winnipeg charges $241 each for new or reused water and sewer connection applications; Calgary's site servicing plan review is $1,533 for the first two reviews; Toronto's technical review for a new or altered connection starts at $440.78. Connection charges and inspection fees come on top.

The cost guide sets these fees beside the connection charges and the private-side work.

07 /What happens after the permit is issued?

The permit starts a chain of bookings. Locates come first; in Alberta, Utility Safety Partners asks for at least three full working days of notice for a routine request. Then the private side is laid and capped at the property line, the city or its contractor builds the public side, and inspections happen before anything is buried. Calgary asks for water utility inspections to be booked at least 48 hours ahead; Saskatoon needs 6 days' notice for right-of-way inspections; Winnipeg forbids backfilling until the City authorizes it.

Finally the records close the file: as-builts, service cards and camera video where required. The inspection guide covers that stage. To see the route for your own city and project, use the Service Connection Planner, or request quotes from contractors who work in your city.

FAQQuestions people ask

Do I need a permit to connect to the city sewer?

Yes. Every city checked requires authorization for any connection to the public system, and a plumbing or servicing permit for the private side. Working on the public side without authorization is not permitted.

Who applies for a sewer connection permit, the owner or the contractor?

For houses, often the owner or builder; for public-side work in Winnipeg, Saskatoon and Calgary, a licensed or approved contractor; for multiplexes in Vancouver and Edmonton, an engineer prepares or stamps the submission.

Is a sewer and water connection permit the same as a building permit?

No. It is a separate approval that often has to be in place before, or alongside, the building permit. Vancouver asks for it before the combined development and building permit.

What drawings does a sewer connection application need?

Usually a site or servicing plan showing proposed and existing services, sizes, slopes and the tie-in point, plus locates. Multiplexes typically add engineered site mechanical, grading and stormwater drawings.

How early should I apply for a new sewer service?

During design. Published waits run from days for some reviews to 12 to 14 weeks in Toronto and 4 to 6 months after the sump inspection in Vancouver, and the city's answers can change the design.

NETWORKGo deeper across the HAUSE Sewer network

Request quotes

Describe the problem once. Get a straight answer.

Send the symptoms and anything you already know — age of the house, what a camera found, what you have been quoted. The HAUSE Sewer desk replies with next steps and, where available, a local contractor for the job.

Sewage backing up right now? Stop using water, keep people away from the water, and do not touch electrical equipment near it.

Tell us about the job

Free request. We read every one and reply by email or phone.

HAUSE Sewer is an independent network, not a contractor. See our privacy notice.

The HAUSE Sewer network

One sewer line, every angle.